Commissioning agent for a new public safety facility

Flathead County

Commission building systems through construction, acceptance, and occupancy of the county’s new public safety facility.

CommissioningBuilding controlsPublic buildings
01

The work

  • Mechanical, plumbing, lighting controls, building automation, and fire detection and alarm systems.
  • Coordinate with the project team during construction, acceptance, and occupancy. Construction began in July 2026 with a stated 30-month timeline.
  • The commissioning authority must attend all required functional tests on site. Critical systems require full testing; repetitive terminal devices may use statistical sampling (Addendum #2, answers 6 and 12).
02

Before you pursue it

  • The designated commissioning authority may be a Montana Professional Engineer in a relevant discipline or a current Certified Commissioning Professional (CCP). A qualified CCP does not also need PE licensure. The authority must belong to the prime firm and meet the RFP’s experience requirements (Addendum #1; RFP pages 8–9).
  • Deliver three printed copies and one disk or USB copy to 800 South Main Street, Room 302, Kalispell, MT 59901 by the deadline. Courier delivery is allowed; late, emailed, or faxed proposals are not accepted (Addendum #2, answer 1).
  • The proposal has a 15-page limit with stated exclusions. Include the signed cover sheet, commissioning experience form, organization chart, and key staff resumes (page 10).
  • Include ordinary travel and other expenses in the fixed fee. State assumptions for site visits, testing, and retesting, and distinguish optional services. Operational-facility access requires background checks and an escort (Addendum #2, answers 10, 13, 14, and 17).

Written questions due5:00 pm; use the RFP’s designated contact.

Question responses issuedAddendum #2 addresses submission, testing, pricing, and site access.

The county has not stated a commissioning fee ceiling. Its construction estimate is not the commissioning contract value.

03